Maintenance
Council has a vigorous maintenance program as part of its commitment to enhancing the Shire’s image and providing a safe community.
Activities included in this cyclic program include grass cutting, road sweeping, litter collection, herbicide application, and graffiti management. The maintenance program also includes roads, footpaths, public toilets, and street lights.
Footpaths & Bikeways
Council repairs and maintains footpaths and bikeways in the shire as part of its commitment to enhancing the shire.
Operational/Capital Roads & Drainage Works
The following Operational and Capital Works have been approved in the 2019/2020 Annual Budget:
LOCATION
|
WORKS BEING PERFORMED
|
ESTIMATED TIME FRAME
|
Waddington-Wongan Hills Road
|
Final Seal (SLK 11.00 - 13.00)
|
October 2019
|
Waddington-Wongan Hills Road
|
Widen to a 8 metre seal (SLK 0.01 - 4.00)
|
January - February 2020
|
Hospital Road
|
Widen to a 8 metre seal (SLK 55.20 - 57.20)
|
September - October 2019
|
Kondut West Road
|
Cement stabilise sub-base and seal (SLK 3.10 - 4.10)
|
October - November 2019
|
Ballidu Bindi Bindi Road
|
Cement stabilise, widen shoulders to 7 metres and re-seal (SLK 23.40 - 25.40)
|
October - November 2019
|
Hospital Road
|
Tree Clearing (SLK 24.50 - 28.90)
|
September 2019
|
Ballidu Bindi Bindi Road
|
Re-seal (SLK 21.80 - 22.80)
|
November 2019
|
Kokardine East Road
|
Gravel re-sheet (SLK 3.20 - 3.70) Clearing (SLK 3.20 - 4.20)
|
|
Ballidu South East Road
|
Gravel re-sheet (SLK 7.50 - 9.50)
|
November 2019
|
Shields Crescent
|
Re-seal (SLK 0.00 - 0.27)
|
March 2020
|
Kondut West Road
|
Repair bitumen edge with profiler and widen shoulders (SLK 0.00 - 2.00)
|
October - November 2019
|
Parker Place
|
Re-seal (SLK 0.00 - 0.20)
|
March 2020
|
Hospital Road
|
Sub-base repairs (SLK 9.20 - 9.80)
|
October 2019
|
Various - Footpath
|
Parker Place (between Quinlan Street and Johnston Street
Stickland Street (between Wandoo Crescent and Patterson Street)
|
November 2019
|
Moonijin West Road
|
Gravel re-sheet (SLK 22.70- 23.70 and 14.40 - 17.40)
|
August 2019
|
Various Roads
|
Tree clearing at various locations throughout the Shire
|
April 2020
|
Kirwan East Road
|
Gravel re-sheet (SLK 1.50 - 5.40)
|
September 2019
|
Central Road
|
Gravel re-sheet (between Melbourne Road and Avon Road)
|
January 2020
|
Manmanning Road
|
Final seal
|
March 2020
|
Gabalong East Road
|
Gravel re-sheet
|
March - April 2020
|
Kondut East Road
|
Re-seal
|
October 2019
|
Vincent Road
|
Gravel re-sheet
|
August 2019
|
Kondut South East Road
|
Re-seal 2.4km and Gravel re-sheet (SLK 5.10 - 7.10)
|
October 2019
|
Townsites
|
Street tree maintenance
|
September 2019
|
Christmas Rock Walk
|
Re-sheet walking paths, update signs, install pipework and clearing
|
July - August 2019
|
Lake Hinds North Road
|
Gravel re-sheet (SLK8.00 - 10.00)
|
March 2020
|
Wongan Hills Sporting Complex
|
Realign Hockey Field
|
October 2019
|
All enquiries to Works Supervisor Stephen Casey on 0438 648 303 or shire@wongan.wa.gov.au.